2x365 MW Lalpir Power Plant





Client Name & Address: Nichimen Corporation, 1-23, Shiba 4-Chome, Minato-18, Tokyo 108, Japan, CPO Box 1136, Tokyo 100-91, Japan
Contact Name & Designation: Mr. N. Yamasaki, Manager, Procurement Section
Telephone & Fax no.: + 81-958-28-4321 (Nagasaki, Japan)
Description of Works: Mechanical, Electrical & Instrumentation Installation works.
Major Quantities: 2 Nos. LP & HP Steam Turbines (MHI) 365 MW each
Generators (Parsons UK) weighing 378 Tons each
Generators & Turbines : 2,060 Tons
Rotary Equipment : 720 Tons
Stationary Equipment : 850 Tons
Steel Structure : 3,300 Tons
Piping : 3,000 Tons
Pipe Supports : 400 Tons
HVAC System : 300 Tons
Pressure Parts : 3,200 Tons
FGD System : 1,120 Tons
CW Piping Erection : 700 Tons
Insulation : 64,000 m2
Painting : 120,000 m2
Total man-hours: 5.0 million
Peak labour force: 2,900
Contract Award Date: February 1996
Project Commencement Date: February 1996
Completion Date: January 1998