Client Name & Address:
|
Foster Wheeler - Foster Wheeler House Station Road Reading Berkshire RG1 1LX,U.K
|
|
Contact Name & Designation:
|
Mr. Roland Davies, Project Manager (Foster Wheeler UK)
|
|
Telephone & Fax no.:
|
Ph: 092-21-572767 Fax: 92-21-570056 (Karachi, Pakistan)
|
|
Location:
|
Qadirpur & Pirkoh Gas Fields, Pakistan
|
|
Owner:
|
Lasmo Oil Pakistan
|
|
Description of Works:
|
Complete Electro-mechanical erection works of 180 mmscfd green-field gas processing plant.
|
|
Major Quantities :
|
Rotary Equipment : 500 Tons
Stationary Equipment : 1,900 Tons
Steel Structure : 500 Tons
Piping : 2500 Tons
Pipe Support : 220 Tons
Painting : 30,000 Sq.M
Insulation : 4,000 Sq.M
Tanks : 200 Tons
|
|
Total man-hours :
|
1.2 million
|
|
Peak Labour Force:
|
900
|
|
Contract Award Date:
|
March 1994
|
|
Project Commencement Date:
|
July 1994
|
|
Completion Date:
|
September 1995
|